It is possible to get value from running a risk analysis regardless of the level of detail in the project schedule. There are often questions which strategy is more proper. Both methods have advantages and drawbacks. This paper will address important factors to keep in mind for both summary schedule and detailed schedule risk simulations.
Listed below are key definitions relative to the typical risk process.
Summary schedules are often seen as easier to manage. The user does not have to worry about auditing and cleaning the detailed schedule. The data will load faster due to the number of activities.
Larger schedules generally require a grouping strategy to reduce the total number of risk inputs. A summary schedule is generally small enough to manually load risk values on each activity. The reduced number of activities also limits the impact of statistical anomalies based on the interaction between large numbers of activities.
Running a summary requires two schedules to be created, updated, and managed in parallel. Summarized logic often creates an issue that the time of the project is represented correctly; however there are not enough activities to create legitimate logic to simulate the ripple effect of risk events.
Risk events from the risk register may not have a proper connection points due to the lack of logical tie-in points. Large lags and excessive start-to-start or finish-to-finish logic is often used in summary schedules. Large lags are hard-coded absences of logic that should often be converted to activities due to their uncertainty. The start-to-start and finish-to-finish logic often causes issues where uncertainty or risk events can be added to an activity yet not create the expected ripple effect.
Using a detailed schedule forces the continuous improvement of working schedule. Over time the amount of schedule cleanup will be greatly minimized. When using a summary schedule, the detailed schedule is usually not given as much attention and will not be cleaned to an appropriate level. This may cause an issue where the schedule quality decreases over time and becomes incredibly time consuming to clean at a later date.
The detailed schedule logic will also contain appropriate tie-in points for risk register items. Uncertainty templates can be created to load risk from a summary level so that the team does not have to individually manage each activity. The templates allow users to create a hybrid analysis approach where uncertainty and risk events are still analyzed from a high level, yet the detailed schedule is utilized. Risk tools have features that will help the user overcome statistical anomalies that can arise due to the number of activities.
Analyzing the detailed schedule is often too time consuming to clean and not worth any additional value based on the required outputs of the risk analysis. Due to the increased complexity of the schedule, any questions about the outputs can be harder to trace or explain. While many of the statistical anomalies can be overcome, many users will still find the level of detail in the summary schedule to be intimidating. If the user is not an experienced scheduler, then this may not be a viable option.
Technology can also be a concern for analyzing a detailed schedule. Current risk analysis tools and computer specifications allow very large schedules to be analyzed, however at a certain point running an analysis on a detailed schedule makes very little sense due to the amount of time needed to process the calculations and the inability of a team to create a perfect logic network.
Copyright © 2021 PRC Software. All rights reserved
This will close in 0 seconds
This will close in 0 seconds
The PRC Enterprise Risk Register is a web-based risk management software solution which allows for the tracking of risk at the project and portfolio level. Audit logs for all risk updates and changes are available at the click of a button to aid with audits, claims and the flow of information. The power of the PRC Enterprise Risk Register is in the simplicity of the user interface, which is designed to navigate easily at both project and portfolio levels without compromising functionality or data. The PRC Enterprise Risk Register allows for mapping across project levels so the data can be reported at the portfolio level, even if the work, risk and organizational breakdown structures are not standardized.
This will close in 0 seconds
The PRC Enterprise Cost Risk Analysis is a customizable web-based solution for simulating estimate cost and determining cost contingency, cost drivers, and risk hotspots. The key to a good risk analysis is good inputs. The software cannot be a roadblock to success. Good risk software should be easy on the end user. Monte Carlo simulation is already a complex. The software should simplify the process.
This will close in 0 seconds
The PRC Enterprise Schedule Risk Analysis is a customizable web-based solution for simulating schedule duration and dates. At PRC Software, we believe that the key to good risk software is through good inputs and excellent user friendliness. A Monte Carlo simulation is already a complex. The software should not be complicated as well.
This will close in 0 seconds
PRC specializes in risk analysis, audit, and training. We have cross-industry experience in fields such as Aerospace & Defense, Oil & Gas, and Engineering & Construction. We believe that over-complicating the risk process often leads to wasted effort and poor results. Our goal is to "make it simple."
This will close in 0 seconds